JCP&L will soon be trimming trees on Quarry Road as well as doing any needed tree removal stemming from damage during the recent storms.  As the day approaches when this work will commence, residents will be notified.

SUEZ
Clinton St at Perry and parts of N Main St and Bridge St should be completed by Friday, April 20.

April 23 - April 26The final disconnections and caps of the water main at Bridge and the Canal, Bridge and S. Main and Bridge and N. Main Streets and final Rte. 179 Service work will be all scheduled for night work around State Roadways.

April 23: Monday we would like to schedule our final connections to Nicolas and services North on 179. This effort is expected to take no more than 2 evenings.

April 25: Wednesday evening, we are looking to start final cut and caps at Bridge and the Canal. 

ELIZABETHTOWN GAS
April 23 - April 27: Soda, the Contractor for Elizabethtown Gas will continue to work on Clinton Street.