Remaining Water Main Construction Work:
South Main Street:
- Abandon connection to 4” main at Swan (remove tee, install spool piece, and transition couplings)
- Abandon connection to 4” main at Ferry (remove tee, install spool piece, and transition couplings)
- Restore grass around newly installed fire hydrant (Northeast corner of S main and Mt. Hope St. Intersection)
- Bury existing 4” valves on abandoned 4” water main (remove top portion of valve box/lid, fill bottom portion of valve box with dense graded aggregate).
- 34 S. Main St (Swan Creek Gallery); Restore sidewalk around curb valve box.
- Roadway restoration as necessary.
- Install additional 8” pipe north and south of the cross to tie-in points at North and South Main St. as per SUEZ sketch.
- Complete tie-in/cut and cap at Bridge and S/N Main St. (two (2) tie-ins).
- Complete water service line work on Route 179. This work may require a new water main crossing across Route 179. Need new sketch.
- Switch 5 services on Route 179 (East Side) after item 3 above is completed.
- Switch (1) services on Rout 179 (west side) around STA. 1+00.
- Complete cut and cap existing 4” water main at Bridge at project origination (station 0+00)
- Abandon the existing 4” water main. Bury existing 4” valves on abandoned 4” water main (remove top portion of valve box/lid, fill bottom portion of valve box with dense graded aggregate).
- Restoration of sidewalk and roadway as necessary.
- SUEZ clarify if any protection bollard need to be installed around new fire hydrants.
Flushing: April 9-25 mostly evenings in the center of town days at Calton and Woodcrest.
2018 New Main Work (SUEZ in design for N Main St for segments between Church and Cherry Sts. (Notice Attached)