Notice Provided by the NJDOT
ALL WORK IN THIS NOTICE IS WEATHER DEPENDENT AND SUBJECT TO CHANGE
Nature of Work: Milling and Paving
Project: Route 179, Route 165 to Route 31/202
Route/Direction/MP: Route 179 / NB & SB / MP 0.38 to 7.34
Municipality/County: City of Lambertville and the Townships of West Amwell & East Amwell / Hunterdon County
Anticipated Traffic Impacts: The Contractor will start the Mill and Pave of Route 179 NB Shoulder/Lane from MP 1.38 to MP 7.34 with a shoulder closing for Paving and a Flagging Operation for paving lanes.
The Contractor will continue with same setup for paving Route 179 SB Shoulder/Lane. For Two Lane section of Route 179 NB/SB from MP 0.38 to 1.38 the Contractor will be closing single lane each direction to perform the Mill and Pave operation. All other Safety improvement work will be performed with Shoulder closing.
Description of New Traffic Pattern: Temporary Closures only
Proposed Start Date of New Traffic Pattern: Monday March 19, 2018 (was Thursday March 8, 2018)
Any other comments: Contractor will begin installation of construction signs with temporary shoulder closings throughout the project. This will begin on or about March 8, 2018.